==== Power plant connection ==== The power plants can be connected to the grid in two ways: |< 700px >| ^ serial with grid power sensor |^ parallel with grid power sensor | | {{ :hiq_energy:hems:hardware:connected_power_plant_in.png?direct400 |}} || {{ :hiq_energy:hems:hardware:connected_power_plant_ex.png?direct400 |}} | When configuring the power plant, select ***in**: serial (**in**ternal) with grid power sensor ***ex**: parallel (**ex**ternal) with grid power sensor The power plants are configured as internal by default. ==== PV inverter ==== Obtaining relevant data from photovoltaic is possible by two ways:\\ 1. adding power-sensor to measure produced electricity by PV (no connection to interver) - on how to add power sensor please see [[en:robotina_charger:commissioning:power_sensor|Power Sensor]]\\ 2. connecting PV inverter by Modbus TCP to EVSE (only for SolarEdge inverters) === EVSE and PV inverter connection === |< 700px >| | {{ :hiq_energy:robotina_charger:rc_pv_inverter_connection_router.png?direct&800|}} | To add inverter on HEMS configurator: * on settings page inside source table, select SolarEdge inverter. Please see [[en:robotina_charger:software#settings|]] * on io mux page set IP address for inverter. Please see [[en:robotina_charger:software#io_mux|]] To setup Modbus TCP on Inverter using SetApp: * Select Site Communication menu * RS485-1 -> Protocol -> SunSpec (Non-SE Logger) * RS485-1 -> Device ID, and enter the number 1 * Modbus TCP and set to Enable * set TCP port to 502 **Note**:\\ The TCP server idle time is 2 minutes. In order to leave the connection open, the request should be made within 2 minutes.\\ It is important to follow rules above, firstly to set HEMS configurator following Inverter setup due to 2 minutes time frame.